Netko me u jednom postu posjetio na ovaj problem BWTS s nekim komentarom ne znam tko je bio da sad repliciram, htio sam replicirat ali nisam se odma sitio kakvo je stanje tocno znam da sam jednom prije par mjeseci komentirao, sad sam malo jos osvjezio znanje kakvo je stanje, mislim da se ne dovoljno to spominje, a ocito ce to bit jedan od dodatnih razloga zbog cega ce suply biti nizi jos dodatno kroz naredne dvi godine, a vjerovatno s peakom u 2022 zbog toga, a moguce je ocekivat i delay u brodogradilistima i bottleneck, s tim da i EEXI brzo stize uz to.
January 5, 2021, by Jasmina Ovcina
Ship classification society Nippon Kaiji Kyokai (ClassNK) said that the installation deadlines based on the BWMS Convention for many of its registered ships are still concentrated in the year 2022.
As of the end of November 2020, 7,220 of the 9,159 ships registered with ClassNK are obligated to install BWMS in accordance with the BWM Convention. Among these, 3,982 ships have completed the installation, leaving 3,238 ships that still require attention.
June 29, 2021, by Fatima Bahtić
In the coming period, global yards are expected to carry out 875 ballast water treatment system (BWTS) installations per month – a roughly 700% increase on the level of recent years.
According to Clarksons Research, around 35,000 vessels still need to install BWTS with only 40 months remaining until IMO’s 2024 deadline.
Large part of global fleet may miss D-2 standard deadline
14 Dec 2021by Craig Jallal
One criteria to meet the D-2 standard ballast water treatment standard is to have an effective ballast water management system (BWMS) installed. With 1,000 days to go, only 22% of the global fleet has done so